Best answer
A Phase I environmental site assessment (ESA) gathers and interprets information to judge whether a property may be contaminated, without sampling, while a Phase II ESA samples and tests to confirm whether contamination is actually present.
- Phase I: follows CSA Standard Z768. It covers preparing for and carrying out an investigation and interpreting and reporting what was found, and it does not involve sampling or analysis.
- Phase II: follows CSA Standard Z769, described as a follow up to Z768. It covers planning sampling, field investigation and measurement, and interpreting and reporting results. It is usually ordered when a Phase I identifies a potential concern.
- Remediation choices and the business decisions that follow are outside the Phase II standard.
Commercial lenders often require a Phase I on commercial, industrial and larger multi unit files. CMHC, for example, requires lender confirmation that the Phase I meets its policy before the first insurable advance on 7+ unit construction. Build time for a possible Phase II into the closing timeline.
General information for mortgage professionals, not legal, tax or compliance advice. Confirm current rules with your regulator or your brokerage's compliance officer.